Main Street Streetscape Redevelopment - Phase II

Share on Facebook Share on Twitter Share on Linkedin Email this link
Concept drawing of new streetscape elements that will be installed on Main Street in Yarmouth.

Beginning in September of 2020, work will get underway on the “Main Street Streetscape Redevelopment - Phase II” as part of the Town’s Downtown Blueprint released in 2010. This major redevelopment project will see important work done above and below ground on Main Street, from Parade Street to John Street. Excavation to replace more of the 100-year-old sewer and underground infrastructure will begin in September.

The project will be completed in two stages. The first will see the complete replacement of sewer and water infrastructure. Much like the Glebe Street sewer separation project, this stage involves replacing the combined rock

Beginning in September of 2020, work will get underway on the “Main Street Streetscape Redevelopment - Phase II” as part of the Town’s Downtown Blueprint released in 2010. This major redevelopment project will see important work done above and below ground on Main Street, from Parade Street to John Street. Excavation to replace more of the 100-year-old sewer and underground infrastructure will begin in September.

The project will be completed in two stages. The first will see the complete replacement of sewer and water infrastructure. Much like the Glebe Street sewer separation project, this stage involves replacing the combined rock sewer with separate sanitary and storm pipes and the installation of a new water service line. By separating the storm water from the sanitary line, the load on the Town’s treatment plant is reduced, as clean rainwater flows directly to the harbour. This reduces electricity use at the plant and the overall level of annual “GHGs” (greenhouse gases) emitted by the town. On the surface, new curbs will be built to accommodate future bumpouts and the entire section of street will receive new asphalt.

The second stage of the project will begin in early spring 2021, and will breathe new life into another section of Main Street. Features will include sidewalk bumpouts enhanced with unique “kitchen party” seating, a new bus shelter, “green” technology planting beds, bike racks, new lighting, and the display of public art. The new streetscape will also provide a dedicated pedestrian clear zone with increased accessibility and the retention of on-street parking. The design concept was developed by Fathom Studio and is a continuation of the theme from Main Street’s Phase 1 Streetscape project completed in 2017. You may visit the project page, view the design in the PDF file "Yarmouth Main Street Council Presentation.pdf" in the "Documents" section to the upper right, or watch the video presentation in the "Videos" section to the upper right.

Keeping you informed

This page has been created to serve as a primary source of information on the project. Our goal is to provide timely updates on progress, answers to your questions, specifics on work being done, and more. While we also plan to communicate through the Town of Yarmouth website, social media and local media, we hope this project page will serve to guide business owners, residents, and visitors on this very important project as it unfolds.

If you would like to speak with us about this work, please contact:

Natalie Smith, Economic Development
902-742-1505 x255

Town of Yarmouth social media links for regular updates:

Facebook: https://www.facebook.com/TownofYarmouth/
Twitter: https://twitter.com/TownOfYarmouth

Stay informed with Alertable notifications:

The Town of Yarmouth is now using a community notification system called "Alertable". Wit Alertable you can receive timely updates on this project and many other topics through the Alertable app, text, email, and more. It's easy, convenient and completely FREE. Learn more and sign up here: https://www.townofyarmouth.ca/alertable.html

  • Street Closure at Collins Street

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Traffic Notice: Street Closure at Collins Street and Main Street Tuesday, May 11th

    As part of the continued work on the Main Street Streetscape Design Project, please be advised of the following:

    ➡ Sawcuts for the north and south side of Collins Street are scheduled for today with demolition beginning tomorrow (weather permitting).
    ➡ Collins Street will be blocked between Main Street and First Street while demolition activities are ongoing.
    ➡ Access to Coastal Financial Credit Union will be maintained via the wheelchair access ramp on Main Street.

    We thank everyone affected for your patience and understanding as we continue work on the Streetscape upgrades.

  • Main Street Streetscape Project Update April 28th, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    Crews are making great progress as the second phase of the Streetscape Design project continues on Main Street. Here's the latest along with closure information:

    • Concrete has been poured for Jenkins Street South & North sidewalks. Sidewalks will soon be open for pedestrian traffic and Jenkins street will reopen for vehicular traffic.
    • Concrete for Lovitt Street South sidewalk will be poured before the end of week, weather permitting.
    • Demolition for Lovitt Street North sidewalk will start tomorrow morning (Thursday).
    • Lovitt Street will be blocked off at the top while concrete and demolition activities are ongoing.
    • Access to businesses in these areas will continue to be maintained as best as possible.
    Thank you to everyone for their patience as the work continues. We're looking forward to seeing the entire project completed in coming months!
  • Main Street Redevelopment Project Resumes Next Month

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Work on Phase II of the Streetscape Redevelopment project is set to begin after Easter Weekend

    Monday, March 22nd - Yarmouth, N.S. – The second phase of a major infrastructure project in downtown Yarmouth is set to begin soon. Following the Easter long weekend, crews will begin work on phase II which will breathe new life into the same section of Main Street. The project is expected to take three months to complete.

    Last fall, the Town replaced sewer and water infrastructure, installed new curbing, and put down new asphalt between Parade Street and John Street to complete phase I of the project. Phase II will see the addition of several beautification pieces, landscaping, and features that enhance accessibility and convenience for pedestrians. Sidewalk bump outs that were added last fall will be enhanced with unique “kitchen party” seating, a new bus shelter (Alma Square), trees and planting beds, bike racks, new lighting, and colorful displays of public art. The new streetscape will also provide a dedicated pedestrian clear zone with increased accessibility and the retention of on-street parking.

    Garian Construction of Yarmouth was awarded the tender to complete the project last fall and is eager to get started.

    “As a local contractor, we’re very proud to have been awarded this project,” said Project Manager Brandon McNicol. “We’re excited to get started and seeing these upgrades underway in our downtown. “

    Yarmouth Mayor Pam Mood is excited to see the second phase start, but also expressed the fact that there will be some disruptions and inconveniences at certain times during the work.

    “This project has been a major undertaking and this second phase will see another area of our downtown completely rejuvenated," said Mood. "While there will be times when areas of the sidewalk will be blocked, along with other disruptions, it's short term and the results will be amazing. It's important that we continue to support our downtown businesses through this."

    Regular updates and notifications on work areas, detours and disruptions from the work being carried out will be provided via the Town of Yarmouth website, social media (Facebook, Instagram, Twitter), and through local media outlets. Updates will also be delivered through “Alertable”, a new community notification system that offers instant updates through a Smartphone app, text, email, and more. It's easy, convenient and completely FREE. Learn more and sign up here: https://www.townofyarmouth.ca/alertable.html


  • Main Street Project Nearing Completion

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    Phase I of the Main Street Streetscape Redevelopment project that began with shovels in the ground on September 24th is nearing completion. It takes significant time and effort to remove and replace underground infrastructure, and despite some minor delays due to weather and obstacles, the project has remained on-track. Phase I of the project should be completed in two weeks time (weather permitting).

    Here's the latest:

    ➡️ All underground water and sewer pipes have been removed and replaced.
    ➡️ Water testing has been completed, and temporary waterlines have been removed.
    ➡️ 4 bump curbs have been completed
    ➡️ Type 2 gravel placement has been completed, with type 1 gravel to be put down next week.
    ➡️ After type 1 gravel is in place, paving commences and, weather permitting, this phase of the project is complete.

    Phase II of the redevelopment will get underway in early April of 2021. This phase involves installing the streetscape elements that will beautify this section of Main Street. The area will feature “kitchen party” seating, a new bus shelter, bike racks, new lighting, the display of public art and more. The new streetscape will also provide sidewalks with increased accessibility and the retention of on-street parking.

    A big thank you to the everyone - especially our downtown businesses - for their continued patience and understanding during this important project. It's been a messy couple of months, but the work is necessary and the improvements will benefit all once complete. #infrastructureupgrades #downtownrevitalization
  • Main Street Redevelopment Project Progressing on Schedule

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Aside from minor delays, replacement of the 100-year-old infrastructure below Main Street is tracking on schedule and set for completion later next month


    Friday, October 23rd, 2020 - Yarmouth, N.S.The latest Main Street Streetscape Redevelopment project is progressing well and on schedule. The first stage of the project involving the complete replacement of sewer and water lines began last month. Aberdeen Paving has carried out the excavation and replacement of the old infrastructure under Main Street, from John Street to Parade Street. Aside form minor delays dealing with unexpected obstacles during the dig, the project has gone well and on track for completion by the end of November.

    Work began on September 24th and is now just past the halfway point. Work to replace the old rock sewer was a major part of the effort and is now complete. Like the Glebe Street sewer separation project recently finished, this “green” project involved replacing the rock sewer with separate sanitary and storm sewers. Separating the storm water from the sanitary line reduces the load on the Town’s treatment plant, as clean rainwater flows directly to the harbour. This will see a significant reduction in electricity use by the plant.

    The next major component is water line replacement which got underway today. Next week will see the continuation of water line work and the following week will see the start of concrete curb work. Once all underground work is completed and gravels and curbing are in place, paving will mark the completion of this first stage in the project.

    Stage two will get underway next spring and involves installation of sidewalk bump outs enhanced with unique “kitchen party” seating, a new bus shelter, “green” technology planting beds, bike racks, new lighting, and the display of public art. The new streetscape will also provide a dedicated pedestrian clear zone with increased accessibility and the retention of on-street parking. The contract for next spring’s work will be tendered this fall.

    ###

  • ‼️WATER DISRUPTION NOTICE‼️

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Please be advised of the following water disruption notice:

    a scheduled water interruption will occur on Friday, October 23rd from 7 am to 12 pm on Central Street, from Main Street to Water Street.

    This interruption in service is necessary as part of the redevelopment project currently underway on Main Street. We thank all of those affected for their patience and understanding.

  • Important Construction Notice: Main Street Closure Extending to Parade Street

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    Work on Main street to replace the more than 100 year old sewer and prepare for the new streetscape is progressing on schedule, and will now move further north from the current work area. Please be advised of the following:

    ➡️ Main Street from Parade Street to Collins Street will be closed beginning Wednesday, October 7th as work progresses to the second block of work
    ➡️ Collins Street from Main Street to First Street will be closed to local traffic only
    ➡️ All other current road blocks will remain in place

    We thank everyone for their continued patience and understanding as we move through this important street infrastructure upgrade
  • ‼️IMPORTANT WATER DISRUPTION NOTICE‼️

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Please be advised of the following scheduled water disruption:

    ➡️ On Wednesday, September 30th, there will be a scheduled water disruption from 7am to 3 pm on Main Street from Parade Street to Central Street.

    This interruption in service is necessary as part of the redevelopment project currently underway on Main Street. We thank all of those affected for their patience and understanding.

  • Work Begin Thursday, September 24th

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CONSTRUCTION NOTICE: Main Street Streetscape Redevelopment - Phase II Work Set for Thursday, September 24th

    With the storm behind us, work can now safely begin on the Main Street Streetscape Redevelopment - Phase II Project. Beginning tomorrow, the following closures/detours will be in effect:

    ➡️ Main Street from John Street to Collins Street will be closed with local traffic only.
    ➡️ Central Street will be closed with local traffic only for access from Water Street.
    ➡️ Jenkins Street will be closed with local traffic only.
    ➡️ Collins Street onto Main Street will be right hand turn only.
    ➡️ John Street onto Main Street will be left hand turn only.

    For complete project details including FAQs, video, and more visit: https://getinvolvedyarmouth.ca/
  • TRANSIT NOTICE: Change of Route Due to Construction

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    IMPORTANT TRANSIT NOTICE: Route Change Begins TOMORROW, September 24th

    Please be advised that the earlier notice reporting a change in route and stop has been changed. The following route change and stop begins tomorrow, Thursday, September 24th:

    ➡️ Travelling north on Main Street, the bus will now turn east onto Cliff Street
    ➡️ It will then turn and travel North on Kirk Street, and then east on John Street to Second Street
    ➡️ On Second Street, it will travel north to Alma Street, then West to First Street, then north to Parade Street and down to Main Street where it will continue northward as usual.
    ➡️ The Stop at Alma Square will be moved to the corner of Alma and First Street. This is the ONLY stop that is affected.

    This route will be in place until further notice. Thank you for your cooperation and understanding.