Main Street Streetscape Project Update April 28th, 2021

Crews are making great progress as the second phase of the Streetscape Design project continues on Main Street. Here's the latest along with closure information:

  • Concrete has been poured for Jenkins Street South & North sidewalks. Sidewalks will soon be open for pedestrian traffic and Jenkins street will reopen for vehicular traffic.
  • Concrete for Lovitt Street South sidewalk will be poured before the end of week, weather permitting.
  • Demolition for Lovitt Street North sidewalk will start tomorrow morning (Thursday).
  • Lovitt Street will be blocked off at the top while concrete and demolition activities are ongoing.
  • Access to businesses in these areas will continue to be maintained as best as possible.
Thank you to everyone for their patience as the work continues. We're looking forward to seeing the entire project completed in coming months!