When does construction start in Yarmouth?

      • Planned to begin on the week of May 12th
      • Construction activities expected to last 4-6 weeks

    What is being done?

      • Installing two, new 180 kW EV Fast Chargers 
      • An EV Charging Site requires a new pole, pad mount utility transformer, and charging equipment (cabinets and transformer) in addition to the chargers
      • Signage and lighting are included in the project

    What will be the disruption to the public?

      • The parking lot may be partially closed during parts of the construction, in particular the Hawthorne Street entry/exit
      • Installation of the new pole may require traffic control for one day on Hawthorne Street
      • Underground primary from new pole to pad mount will cross the sidewalk on Hawthorne Street 
        • For 2-3 days the sidewalk will be blocked off and cars will not be able to park in the leased, adjacent parking area  
      • Fencing off six parking spaces (which will become four EV Charging spaces)
      • Contractor will need an area to leave machinery and equipment

    What changes are occurring to the parking lot?

      • Six regular parking spaces will be converted to four EV fast charging spaces
      • Any trenching/excavation will be restored, including new asphalt on for the new charging spaces

    Will new parking spaces be created to offset the loss of stalls?

      • New parking spaces are being proposed to maintain as much parking capacity as possible, besides adding EV fast charging spaces.

    When are the EV chargers expected to be available for public use?

      • Expected to be available for use by mid to late June