Haley Road Multi-use Trail Update: Paving of First 300 Metre Section

The weather has cooperated in recent weeks and work has progressed quickly on the multi-use trail between Forest Street and Argyle Street on Haley Road. As work continues, please be advised of the following:

➡️ Fine grading is nearing completion for the first 300 metres of the completed trail, beginning at Forest Street heading south.
➡️ Paving of the section is set to take place between Friday, June 10th and Tuesday, June 14th 2022, but is WEATHER DEPENDENT.
➡️ Local residents can expect to experience driveway interruptions as the work progresses.
➡️ Traffic control will be in place during paving.

More updates will be provided as we get closer to the end of the week. We again thank everyone involved for their patience and understanding as we add this much-needed active living trail/sidewalk to the area.

Share Haley Road Multi-use Trail Update: Paving of First 300 Metre Section on Facebook Share Haley Road Multi-use Trail Update: Paving of First 300 Metre Section on Twitter Share Haley Road Multi-use Trail Update: Paving of First 300 Metre Section on Linkedin Email Haley Road Multi-use Trail Update: Paving of First 300 Metre Section link